|
Press
Release # 1

One of the Umlass Trunk Sewer Extension pipe bridges with the
Trio formwork in place for the last pour.
|
|

Contract Manager Syd van Schoor
|
|
Peri Trio
Wall Formwork Proves Itself on Umlaas Trunk Sewer Extension
- Contractors: Murray
& Roberts Construction & Makhuba Civils
- Contracts
Manager: Syd van Schoor
- Consulting
Engineers: Stewart Scott
- Client: Ethekwini
Metro Waste Water Services
The construction
of two pipe bridges on the Umlaas Trunk Sewer Extension contract
outside Durban was causing headaches for contractors Murray &
Roberts Construction and Makhuba Civils until Peri Wiehahn stepped
in to provide a cost-effective solution.
The contract called for the construction of two pipe bridges across
the Umlaas River and stipulated that these should do double duty
by acting as foot bridges across the river for the benefit of the
communities living in the surrounding areas.
Murray & Roberts Contract Manager Syd van Schoor explained that
the design of the two bridges called for them to be cast in concrete
with sewage pipes running through their middles preventing tie-rods
from being used to help support the shutters on the sides of the
bridges.
After being called-in to suggest a solution to the problem Peri
Wiehahn Durban Branch Manager Gerhard Moll recommended that the
Peri Trio Wall Formwork System be used with the bridge sides being
formed by two shutter panels supported at the join with compensating
steel walers and tie-rods being used only above and below the bridge
structure.
The contractors took the decision to implement the suggestion and
ordered two sets of Trio Formwork components to enable the construction
teams to work on both bridges simultaneously. The formwork was delivered
to the site shortly afterwards and an immediate on-the-job training
programme was instituted for the construction team by Peri Wiehahn's
Durban Branch staff.
Mr van Schoor said that his first impression of the Trio System
was how much faster it was to erect than conventional formwork systems
due to the fact that it requires far fewer elements such as couplers
and tie-rods. The system's simplicity was also instrumental, he
said, in minimising training time and allowing its use by unskilled
and semi-skilled labour.
An eye-opener for Mr van Schoor was how effective the self-aligning
feature built into the system was with the alignment of the shutters
taking a fraction of the time that would have been required if conventional
formwork had been used on the job.
The bridge contractors had another very pleasant surprise in store
when it was found that the system allowed them to erect and strip
the formwork so rapidly once it was gang-formed that they were able
to return one set of components to Peri Wiehahn for credit and shuttle
the other set between the bridges using a mobile crane.
The mobile crane was disabled just before it was required to move
the formwork from one bridge to another for the pouring of the final
span but it took only one extra day to move in spite of the fact
that the forwork had to be completely dismantled, moved to the other
bridge and re-erected.
Another very impressive feature of the Trio System, according to
Mr van Schoor, was the very high quality of the off-shutter finish
provided by the system with that on the sides of the bridges being
markedly better than the bridge soffits and other areas where conventional
formwork was used.
Mr Moll explained that the Trio shutter panels are lined with a
phenolic resin-coated plywood which provides an extremely high quality
finish to concrete and that this is enhanced by the fact that the
BFD coupler fastens the panels together so securely that the joints
are grout-tight thus ensuring that the finish obtained is of the
highest possible quality.
The contractors on the Umlaas Trunk Sewer Extension project have
joined the growing list of Peri Wiehahn clients in South Africa
who have found that, by using Peri products, they can save up to
50% of the time they would have needed if they had used conventional
formwork systems. According to Mr Moll the ease of use of the Peri
products makes for much faster cycle times which has a positive
impact on the speed at which contracts are completed and thus lead
to major reductions in costs.
ENDS
|